Tag Archives: MS PROJECT 2013

Fiscal Year and MS PROJECT 2013

Hi, some of you told me that there is something wrong in MS PROJECT 2013 when displaying dates in Gantt Chart. Well, the solution is in Fiscal Year Settings. For  some companies Fiscal Year is equal to Calendar Year (e.g. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment

Resource Pool and Local Resources in MS PROJECT 2013

  Hi, I have a question from one of my Blog readers: “Hello, Nenad. First, I’d like to thank you by your posts. They are very helpful. Now, to my question. I have a central team coordinating and working in … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, PMI, PRoject Management | Tagged , , , , , | 2 Comments

Calendars and Moving Tasks to non working days in MS PROJECT 2013!

  Hi, again I have a question from my Blog Reader: “I liked your article and thought you may have an answer to a question I have.In Project 2010 with tasks set to Auto schedule if you schedule the start … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 3 Comments

How to show separate costs for people and material in MS PROJECT 2013

  Hi, another question form my Blog Reader: “For a particular task, Can we get the material cost and labor cost separately for that particular day?, and can we display the material resources and work resources separately in the task … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment

Resource over-allocation and Gantt chart in MS PROJECT 2013!

  Hi, one of my Blog readers ask me this: “Hello, could you please advice…you all seem to be very experienced with MS. ‘m interested in resource management. I tried to apply MSP and found that I’m not able to … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, PMI, PRoject Management | Tagged , , , | 4 Comments

Splitting Tasks again in MS PROJECT 2013

  Hi, I’ve got a question from one of my Blog Readers: “’I’m looking for a more precise method (non-graphical?) to set up the splits. For example I want to split a 10-work-day task halfway through, and have work resume … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | 2 Comments

How to make modified Calendar default for future Projects in MS PROJECT 2013!

  Hi, here is the question from my Blog reader: “Is there a way to change the default calendar so that every new project is created with the predefined working time?” Let me show you how can you accomplish that! … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 4 Comments

Slack (or Float) types in Microsoft Project 2013, Part 2

  Hi, Let us continue with Slack story in MS PROJECT 2013. First I will create a new Project with Task List: Because picture is too big I will show you the Gant Chart: Now, again I will apply the … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , , | Leave a comment

Slack (or Float) types in Microsoft Project 2013, Part 1

  Hi, Today I am going to explain slack, or float in MS PROJECT 2013. There are two types of slack in MS PROJECT 2013: Free slack: The free slack of an activity is the time this activity can be … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | Leave a comment

Overtime, Costs, and Fixed Duration in MS PROJECT 2013

Hi, I got this issue from my Blog Reader: “OK. I am entering in hours in overtime work field as the instructions note but when I view the cost table, only the regular hours are calculated in the cost. This … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, PRoject Management | Tagged , , | Leave a comment