-
Recent Posts
Archives
- May 2013
- April 2013
- March 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
- September 2012
- August 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
- January 2012
- December 2011
- November 2011
- October 2011
- September 2011
- August 2011
- July 2011
- June 2011
- May 2011
- April 2011
Categories
Meta
Monthly Archives: February 2012
Manually Scheduled Summary Tasks, and how to deal with them!
Hi, I will show you how to deal with Manually Scheduled Summary Tasks in MS PROJECT 2010! As you already know Manually Scheduled Task are new feature in MS PROJECT 2010, and those tasks are fully controlled by you. … Continue reading
Backstage in MS PROJECT 2010! What do we have here?
Hi, in Backstage View in Microsoft Project 2010 you can setup many parameters for using MS PROJECT 2010. I will cover some of them, because if I want to cover them all, this Post will be very, very long. … Continue reading
How to track Actual overtime work in MS PROJECT 2010
Hi, I received a question from one of my Blog reader: “After calculating the costing for work and overtime work, I baselined the task and then did tried to do the actuals in the task usage sheet. I did … Continue reading
How to create and use Templates in MS PROJECT 2010?
Hi, You can use MS PROJECT 2010, for various Project types (software development, event organization, production, construction, etc.). For each new Project (of same type), you can build your task, schedule, resource pool, assignments, costs, reports, etc. fro the … Continue reading
Working with Graphical Indicators in MS PROJECT 2010
Hi, in this Post I’ll show you how to use graphical Indicators in MS PROJECT 2010. Here is The Scenario: I have may Project Baseline (and this is my Project Plan) I am tracking the Project Progress If my … Continue reading
How to work with Outline Codes in MS Project 2010?
Hi, in my last Post I have explained how to use custom fields in MS PROJECT 2010. One of custom field type is Outline Code. Suppose that you have resources group by skills like this: Developers (101 – C# … Continue reading
Customizing fields and specifying Lookup Values for a Custom Fields
Hi, in this Post I will explain how to use custom fields in MS PROJECT 2010. There are nine types of Custom Fields in MS PROJECT 2010: Cost. Use this type when you need a field in which you … Continue reading
Customizing Views in MS PROJECT 2010 – Part 2.
Hi, in my previous Post I have explained how to copy one View to another, and make a customization. Notice that are two different types of View in MS PROJECT 2010: Single View, and Combination View. Example of Single … Continue reading
